The challenge
A university research and laboratory building runs an 800 ton chilled water plant, two 400 TR chillers and two cooling towers.
The plant held condenser water near 66 °F with a fixed setpoint, whatever the weather. The tower fans ran at a median 88% speed, and both towers ran together most of the time, so fan energy stayed high even when conditions would have allowed far less.
One control change, no new hardware, and a result measured against the plant's own data.
Site profile
Verified results
Annual, cooling mode, IPMVP Option B
Measured from 3 June to 15 August 2026 against a baseline adjusted for cooling delivered and weather, then applied to a full year of plant data. Savings cover both chillers and both cooling tower fans. No cost saving is reported for this site.
| Annual, cooling mode | Before | After | Saved |
|---|---|---|---|
| Plant energy (kWh) | 577,495 | 496,663 | 80,832 |
| Plant efficiency (kW/ton) | 0.809 | 0.696 | 0.113 |
Emissions avoided: 29.3 tCO2e per year, from the annual energy saving.
Over the measured period, 3 June to 15 August 2026, the plant used 15.35% less energy than the adjusted baseline, 34,358 kWh lower, and every day compared used less energy. The annual figure of 14.0% applies the same improvement to a full year of plant data, so it also covers the cooler months the summer measurement did not see.
Where the saving came from
Fans saved far more than the chillers gave back
| Cooling tower fans | Before | After |
|---|---|---|
| Median fan speed | 88% | 43% |
| Time at full speed | 44% of running time | Almost none |
| Both towers running together | 64% | 29% |
Fan energy fell 79%. Fan power follows the cube of speed, so a modest drop in speed removes a large share of the energy.
| Chillers | Before | After |
|---|---|---|
| Lift | 25.5 °F | 30.6 °F |
| Chiller kW/ton | 0.610 | 0.649 |
| Chilled water supply, median | 43.1 °F | 43.1 °F |
Warmer condenser water made the chillers work harder, using 6.4% more chiller energy per ton of cooling. The fan saving was about four times larger.
| Annual, cooling mode | Before | After | Change |
|---|---|---|---|
| Tower fan energy | 138 MWh | 29 MWh | −108,840 kWh |
| Chiller energy | 439 MWh | 467 MWh | +28,008 kWh |
| Total plant energy | 577,495 kWh | 496,663 kWh | −80,832 kWh |
Chiller kW/ton is weighted by cooling delivered. Fan and chiller energy in MWh are rounded.
How the result was measured
The measurement boundary covers both chillers and both cooling tower fans. Summer 2026 was compared against an adjusted baseline built from a regression of daily plant energy on cooling delivered and weather, with an R² of 0.96.
The annual figure sorts every 5-minute interval by wet bulb and cooling load, compares kW/ton before and after inside each matched band, and applies the improvement to the baseline year.
What sits outside the figure
Pump energy is outside the measurement boundary. It ran the same in both periods, so it does not change the result.
Chilled water supply temperature held at a median 43.1 °F before and after the change.
The Exergenics approach
One change, programmed by the site's own team
Model the plant from its own data
Exergenics modeled a year of the building's BMS trend data.
Replace the fixed setpoint
The fixed condenser water setpoint was replaced with a reset that follows wet bulb and cooling load.
Programmed by the site's own controls team
The facility's controls team programmed the reset into the existing BMS in June 2026. No hardware was added.
Measure against the adjusted baseline
Savings were measured to IPMVP Option B over summer 2026 and applied to a full year of plant data by matching weather and cooling load.