CASE STUDY · HIGHER EDUCATION

University research facility chiller plant optimization, US Northeast

Condenser water that follows the weather. A dynamic reset, programmed into the BMS the building already had, cut cooling-mode plant energy 14.0% across a full weather year at an 800 TR university research plant, measured to IPMVP Option B. No hardware was added.

Wide, dimly lit interior corridor with a polished wood floor and floor-to-ceiling glazing, a person walking toward the camera
University research facility
Illustrative image. Photo: simonlaunay on Unsplash
Location
US Northeast
Sector
Higher education
Plant capacity
800 TR
Commissioned
June 2026
M&V
IPMVP Option B

Energy saving

14.0%

Less cooling-mode plant energy, measured in summer 2026 and applied to a full year

Energy saved

80,832kWh

Per year, from 577,495 kWh down to 496,663 kWh

Carbon avoided

29.3tCO2e

Per year, from the annual energy saving

Plant efficiency

0.696kW/ton

Down from 0.809 kW/ton before the change

The challenge

A university research and laboratory building runs an 800 ton chilled water plant, two 400 TR chillers and two cooling towers.

The plant held condenser water near 66 °F with a fixed setpoint, whatever the weather. The tower fans ran at a median 88% speed, and both towers ran together most of the time, so fan energy stayed high even when conditions would have allowed far less.

One control change, no new hardware, and a result measured against the plant's own data.

Site profile

Facility type
University research and laboratory building
Location
US Northeast
Plant
2 × 400 TR chillers, 2 cooling towers
Controls
Existing BMS, programmed by the site's controls team
Strategy
Dynamic condenser water temperature reset
Baseline
March 2025 to March 2026
Commissioned
June 2026
Measured
3 June to 15 August 2026, applied to a full year of plant data
Data
5-minute BMS trends
Hardware
None added
Site
University research facility, US Northeast

Verified results

Annual, cooling mode, IPMVP Option B

Measured from 3 June to 15 August 2026 against a baseline adjusted for cooling delivered and weather, then applied to a full year of plant data. Savings cover both chillers and both cooling tower fans. No cost saving is reported for this site.

Annual, cooling modeBeforeAfterSaved
Plant energy (kWh)577,495496,66380,832
Plant efficiency (kW/ton)0.8090.6960.113

Emissions avoided: 29.3 tCO2e per year, from the annual energy saving.

Over the measured period, 3 June to 15 August 2026, the plant used 15.35% less energy than the adjusted baseline, 34,358 kWh lower, and every day compared used less energy. The annual figure of 14.0% applies the same improvement to a full year of plant data, so it also covers the cooler months the summer measurement did not see.

Where the saving came from

Fans saved far more than the chillers gave back

Cooling tower fansBeforeAfter
Median fan speed88%43%
Time at full speed44% of running timeAlmost none
Both towers running together64%29%

Fan energy fell 79%. Fan power follows the cube of speed, so a modest drop in speed removes a large share of the energy.

ChillersBeforeAfter
Lift25.5 °F30.6 °F
Chiller kW/ton0.6100.649
Chilled water supply, median43.1 °F43.1 °F

Warmer condenser water made the chillers work harder, using 6.4% more chiller energy per ton of cooling. The fan saving was about four times larger.

Annual, cooling modeBeforeAfterChange
Tower fan energy138 MWh29 MWh−108,840 kWh
Chiller energy439 MWh467 MWh+28,008 kWh
Total plant energy577,495 kWh496,663 kWh−80,832 kWh

Chiller kW/ton is weighted by cooling delivered. Fan and chiller energy in MWh are rounded.

How the result was measured

The measurement boundary covers both chillers and both cooling tower fans. Summer 2026 was compared against an adjusted baseline built from a regression of daily plant energy on cooling delivered and weather, with an R² of 0.96.

The annual figure sorts every 5-minute interval by wet bulb and cooling load, compares kW/ton before and after inside each matched band, and applies the improvement to the baseline year.

What sits outside the figure

Pump energy is outside the measurement boundary. It ran the same in both periods, so it does not change the result.

Chilled water supply temperature held at a median 43.1 °F before and after the change.

The Exergenics approach

One change, programmed by the site's own team

1

Model the plant from its own data

Exergenics modeled a year of the building's BMS trend data.

2

Replace the fixed setpoint

The fixed condenser water setpoint was replaced with a reset that follows wet bulb and cooling load.

3

Programmed by the site's own controls team

The facility's controls team programmed the reset into the existing BMS in June 2026. No hardware was added.

4

Measure against the adjusted baseline

Savings were measured to IPMVP Option B over summer 2026 and applied to a full year of plant data by matching weather and cooling load.

Put a number on your own campus plant

Exergenics optimizes chilled water plants for universities, hospitals, airports and commercial portfolios. No capital expenditure, no hardware and no security review.

Figures come from an IPMVP Option B measurement and verification study using 5-minute BMS trends, measured 3 June to 15 August 2026 against a baseline adjusted for cooling delivered and weather, and applied to a full year of plant data.