CASE STUDY · HEALTHCARE

Chilled water plant optimization at Queensland Children's Hospital, Brisbane

Light-touch controls recommendations from an Exergenics digital twin of the hospital's 17,700 kWr central energy plant were deployed by the site team in March 2022. Plant efficiency improved 3.3% a year, measured to IPMVP Option B, with no disruption to patient care and no new hardware.

Queensland Children's Hospital in South Brisbane, with green and purple vertical fins across its facade above a tree-lined street corner
Queensland Children's Hospital, South Brisbane
Tertiary pediatric hospital served by a central energy plant
Client
Queensland Children's Hospital
Location
Brisbane, Australia
Sector
Healthcare
Plant
17,700 kWr, 6 water-cooled chillers
Implemented
March 2022

Efficiency improvement

3.3%

Chilled water plant efficiency, per year, IPMVP Option B

Emissions reduced

41tCO2

Per year, as reported in the M&V summary

Operating cost saving

$28,000

Per year, as reported in the M&V summary

Hardware added

None

Recommendations deployed by the site team in the existing controls

The challenge

Queensland Children's Hospital in South Brisbane is a working tertiary pediatric hospital. Its central energy plant supplies chilled water to the main hospital building and the Centre for Children's Health Research. The plant has one 1,100 kWr low-load variable-speed centrifugal chiller and five 3,315 kWr variable-speed centrifugal chillers, configured for N+1 redundancy.

In a hospital, cooling is not optional, so any change to the plant has to cut energy and carbon without affecting patient comfort or causing disruption. With five large identical chillers and one smaller chiller, how the plant stages and shares load across them decides how efficiently it runs.

The aim was to decarbonize the plant's operation without touching patient comfort or adding hardware.

Site profile

Client
Queensland Children's Hospital
Location
South Brisbane, Queensland, Australia
Facility type
Tertiary pediatric hospital and research center
Chillers
1 × 1,100 kWr and 5 × 3,315 kWr Trane variable-speed centrifugal, N+1
Cooling capacity
17,700 kWr
Data source
The hospital's data warehousing platform, with input from the FM team
Implementation
Site team, March 2022
Capital expenditure
Nil
M&V protocol
IPMVP Option B, 12 months

Verified results

Measured over 12 months after implementation

Measurement and verification followed IPMVP Option B over 12 months after the site team deployed the recommendations in March 2022. Emissions and operating cost figures are as reported in the Exergenics M&V summary for the site.

OutcomeResultStatus
Efficiency improvement3.3% improvement in chilled water plant efficiency per yearVerified
Emissions reduced41 tCO2 per yearVerified
Operating cost saving$28,000 per yearVerified
Patient comfortNo disruption reported during or after implementationObserved
Pre-implementation study7.1% energy and 5.4% peak demand, simulated by the digital twin across a year of historical dataModeled

The modeled figure comes from the 2021 QUT technology evaluation for i-Hub, which simulated all three recommendations together before any change was made. The verified figures measure the plant as it ran after the site team's deployment.

The Exergenics approach

A digital twin, then recommendations for the site team

Exergenics doesn't write to the BMS. The recommendations went to the hospital's site team, who deployed them in the existing controls.

1

Data and documentation

A year of plant data came from the hospital's data warehousing platform: chiller energy, cooling load, temperatures and flow rates. The facilities management team flagged plant details that the data alone didn't show.

2

Build the digital twin

Machine learning models of each chiller, pump and cooling tower were combined into a model of the whole plant and checked against a randomized 20% holdout of the data. The model was assessed independently by QUT as part of i-Hub's Healthcare Living Laboratories program, funded by ARENA.

3

Develop the strategy

Exergenics adjusted the model's constraints with feedback from the site, then optimized the plant at every load and weather condition. The recommendations covered chiller staging, a dynamic condenser water temperature reset and load balancing between the small and large chillers.

4

Implement and verify

The site team deployed the recommendations in March 2022. Savings were measured to IPMVP Option B over the following 12 months.

Find the savings in your plant

Exergenics works with the data your building already collects. No capital expenditure, no new hardware and no disruption to operations.

Results were measured to IPMVP Option B over 12 months after implementation in March 2022. The modeled figure is from QUT's 2021 technology evaluation for i-Hub (Report LLHC4-003).