University of Melbourne Chiller Optimization | Exergenics

Case Study — Higher Education

University Campus Chiller Plant Optimization at the University of Melbourne

Fourteen chilled water plants across the Parkville and Southbank campuses, optimized building by building. Nine have completed twelve month measurement and verification, and between them they are saving 62% more energy than the models forecast.

Location
Melbourne, Australia
Sector
Higher Education
Buildings
14 contracted, 9 verified
Plant Capacity
35,592 kWr
Delivered
2021 to 2025

Verified energy saved

426,444 kWh

Per year, across the nine buildings that have completed M&V

Verified carbon abated

269 tCO2

Per year, at the 2025 NEM scope 2 and 3 factor of 0.63 tCO2/MWh

Against modelled forecast

+62%

Measured savings exceeded the modelled forecast of 262,571 kWh

Buildings verified

9 of 14

The remaining five are modelled and awaiting verification

The Challenge

Fourteen plants, fourteen different problems

A university campus is not one building repeated. The University of Melbourne runs chilled water plants serving a neuroscience research facility, a rare books library, a performing arts school, a biocontainment institute and a law school, and each of those has a different load profile, a different tolerance for variation and a different set of constraints on what the plant is allowed to do.

Plant capacity across the portfolio ranges from 1,198 kWr at the Nancy Millis Building to 5,300 kWr at the Peter Doherty Institute. Chiller counts range from two to three. Some plants serve laboratories that cannot deviate. Others serve teaching space that empties for months at a time.

A single control philosophy applied across all of them would have been simpler to deliver and would have left most of the saving on the table. The university's energy team wanted each plant tuned to its own building, and wanted the results measured rather than asserted.

Every building was modelled on its own data, and every result reported here was measured against that building's own pre implementation baseline.

Portfolio Map

Where the savings are

Twelve of the fourteen buildings sit on the Parkville campus and its Carlton edge. The remaining two are at Southbank, home of the Faculty of Fine Arts and Music.

Aerial photograph of the University of Melbourne Parkville campus looking south east toward the Melbourne CBD, with twelve optimized buildings marked. Optimized buildings on the University of Melbourne Parkville campus Markers over an aerial photograph showing each optimized building and its verified annual energy saving. The two Southbank buildings are on a separate campus and are listed in the key below. 110 The Spot 45,415 kWh 379 Bouverie St 29,679 kWh 106 Law Building 12,545 kWh 248 Peter Doherty 69,961 kWh 401 Nancy Millis 50,417 kWh 144 Kenneth Myer 126,321 kWh 168 Doug McDonell 26,333 kWh 110 379 106 248 401 144 168 133 153 177 105 104 PARKVILLE CAMPUS Verified annual savings shown. Grey markers are modelled, M&V pending.
Marker positions are indicative. The two Southbank buildings, 880 MCM Performing Arts and 864 Dance Building, are on a separate campus 2.5 km south and are listed in the key below.
Verified Modelled, M&V pending
  • 144Kenneth Myer, Neurosciences126,321 kWh verified
  • 248Peter Doherty Institute69,961 kWh
  • 401Nancy Millis50,417 kWh
  • 110The Spot45,415 kWh
  • 864Dance Building, Southbank42,311 kWh
  • 379207 Bouverie Street29,679 kWh
  • 168Doug McDonell26,333 kWh
  • 880MCM Performing Arts, Southbank23,462 kWh
  • 106Law Building12,545 kWh
  • 177Baillieu Library43,863 kWh modelled
  • 153Chemistry, West Wing26,245 kWh modelled
  • 105Business & Economics19,141 kWh modelled
  • 104Alan Gilbert17,960 kWh modelled
  • 133Glyn Davis, Melbourne School of Design16,943 kWh modelled

Verified Results

Nine buildings, measured over twelve months

Modelled savings are the forecast issued before implementation. Verified savings were measured over a twelve month reporting period against each building's own baseline. Carbon is converted at 0.63 tCO2/MWh, the 2025 NEM scope 2 and 3 factor for the Victorian grid. Per building carbon figures are rounded to whole tonnes, so the column does not sum exactly to the portfolio total, which is computed from total kWh.
Building Plant Modelled kWh Verified kWh Verified tCO2 Against forecast
144 Kenneth Myer, Neurosciences4,200 kWr46,048126,32180+174%
248 Peter Doherty Institute5,300 kWr60,76169,96144+15%
401 Nancy Millis1,198 kWr51,92950,41732−3%
110 The Spot2,280 kWr20,83945,41529+118%
864 Dance Building, Southbank1,900 kWr38,99142,31127+9%
379 Building, 207 Bouverie Street1,240 kWr9,73929,67919+205%
168 Doug McDonell2,874 kWr14,20026,33317+85%
880 MCM Performing Arts, Southbank1,370 kWr13,43123,46215+75%
106 Law Building3,200 kWr6,63312,5458+89%
Nine buildings verified 23,562 kWr 262,571 426,444 269 +62%

Reading the Numbers

Why the measured savings ran ahead of the model

Eight of the nine verified buildings beat their forecast, and the portfolio came in 62% above the modelled total. That gap is worth explaining, because a model that is wrong by 62% in the other direction would be a serious problem.

Exergenics models carry a deliberate factor of safety. The forecast issued to a client is the saving the plant should deliver under conservative assumptions about load, weather and how faithfully the strategy gets implemented. It is written to be a floor, not a midpoint.

Two things then move the measured result above it. Cooling demand in the reporting period is rarely identical to the baseline period, and where demand rose the optimized plant absorbed it more efficiently than the baseline plant would have. And several of these buildings had more headroom in condenser water control than the conservative model assumed.

The Nancy Millis Building is the useful counter example. It came in 3% under forecast, which says the model was close and the plant had less slack than the others. A portfolio where every building overshoots by the same margin would suggest a systematic modelling bias rather than genuine site by site variation.

In Progress

Five buildings modelled, verification scheduled

The third tranche completed modelling and implementation and has not yet been through measurement and verification. The figures below are forecasts, not measured results, and should be read as such.

Modelled forecast only. No measurement and verification has been completed for these buildings. Carbon figures are rounded to whole tonnes, so the column does not sum exactly to the total.
Building Plant Modelled kWh Modelled tCO2 Status
177 Baillieu Library3,500 kWr43,86328M&V pending
153 Chemistry, West Wing2,500 kWr26,24517M&V pending
105 Business & Economics2,500 kWr19,14112M&V pending
104 Alan Gilbert1,880 kWr17,96011M&V pending
133 Glyn Davis, Melbourne School of Design1,650 kWr16,94311M&V pending
Five buildings modelled12,030 kWr124,15278

The Exergenics Approach

Optimization inside the university's own control system

Nothing was installed on the university network. Each strategy was delivered as setpoints and sequences for the incumbent controls contractor to code into the existing building management system.

  1. Model each plant on its own data

    Historical chiller, pump and cooling tower trends were drawn from each building individually. Plant that shares a campus does not share a load profile, and a model built on one building's data does not transfer to the next one along.

  2. Generate a strategy the plant can actually run

    Chiller staging thresholds and condenser water temperature control were generated for each plant and bounded by constraints the site team confirmed. Research and teaching buildings on this campus have hard limits on how far conditions may drift, and the strategy respects them rather than optimizing past them.

  3. Implement through the incumbent contractor

    The university's incumbent controls contractor coded the recommended strategies into the existing BMS. No hardware was added, no gateway was installed and no external connection to the control network was required.

  4. Verify against the building's own baseline

    Each verified building was regressed against measured cooling load over a twelve month reporting period and compared with its pre implementation baseline on the same basis. The portfolio figures in this case study were compiled by the university's energy consultants.

Put a number on your own campus

Exergenics optimizes chilled water plants for universities, hospitals, airports and commercial portfolios. No capital expenditure, no hardware and no disruption to operations.

Talk to an expert Download case study PDF

Verified figures are drawn from twelve month measurement and verification reports and from the portfolio comparison of forecast against realised savings compiled by the University of Melbourne's energy consultants, July 2025. Carbon conversion uses 0.63 tCO2/MWh, the 2025 NEM factor for scope 2 and 3 emissions.